The Work Before the Work

cory2979
Oct 8
7 min read

The North has the opportunity. Readiness will decide what gets built.


For most of my lifetime, Northerners have been making the same case to Canada: if you want a stronger and more secure country, you need to invest in the North. For long periods, that argument struggled to receive sustained national attention. Today, Arctic security, critical minerals, energy, transportation corridors and nation-building infrastructure have moved to the centre of the national conversation.


The Mackenzie Valley Highway, Arctic Economic and Security Corridor, and Taltson Hydro Expansion are now before Canada’s Major Projects Office. Defence investments are being planned for Yellowknife and Inuvik. Communities are preparing for new housing, infrastructure, workers and economic activity. After years of asking Canada to pay attention, the attention has arrived.


That is good news, but it creates a different challenge. The next Northern infrastructure problem may not be finding projects worth building. It may be getting those projects ready quickly enough to take advantage of the opportunity in front of us.


Announced Is Not the Same as Ready


From a distance, a major funding announcement can look like the beginning of construction. A project receives federal recognition, a minister announces funding, a map is released or the project appears in a government budget or mandate. People understandably assume equipment will soon be moving.


Those are important milestones, but they are not construction schedules. Canada recently committed $405 million to advance the Mackenzie Valley Highway. That is a significant investment in a project Northerners have discussed for generations, but “advance” is an important word.


A highway extending through the Mackenzie Valley still requires decisions about routing, engineering, environmental review, Indigenous participation, community impacts, procurement, construction sequencing and long-term maintenance. The public announcement is visible; much of the necessary work that follows is not.


The same applies to energy projects, defence facilities, mines, housing developments and community infrastructure. A project may have political support without having a completed business case. It may have funding without having a delivery team, or a preliminary design without having land, permits or an operating plan. That does not necessarily mean something has gone wrong. It means an announcement and a project are not the same thing.


A Shovel Is Not a Project Strategy


A couple of years ago, I wrote about helping Northern communities get capital projects closer to being “shovel-ready.” The point was that when funding programs open, communities with stronger planning, clearer scopes and more advanced designs are generally better positioned to apply and move forward.


I still believe that, but the phrase “shovel-ready” can make project readiness sound simpler than it is. In the North, a shovel is not much use if the land remains unresolved, the geotechnical work is incomplete, the construction materials have missed the barge or no one has determined who will operate and maintain the road after it opens.


A project is not ready simply because its design has reached a certain percentage. It is ready when the project owner understands the need, the ownership, the partnerships, the approvals, the risks, the cost, the delivery plan and what happens after construction. Not every question needs a final answer, and major projects will always carry uncertainty, but the project needs a credible path through those questions.


Project Owners Need to Be Ready Too


Readiness is not only about the project. The government or organization responsible for delivering it also needs the people, authority and structure to manage the work.


We are already seeing governments in the Northwest Territories prepare themselves differently. The GNWT established a Strategic Infrastructure, Energy and Supply Chains team with dedicated senior leadership focused on the Mackenzie Valley Highway, Taltson Hydro Expansion and Arctic Economic and Security Corridor. The City of Yellowknife has established a Major Projects and Opportunities Secretariat to coordinate significant infrastructure and development connected partly to proposed DND investment.


The GNWT is also examining the creation of an arm’s-length agency to oversee delivery of the Mackenzie Valley Highway. The final structure has not yet been determined, but the intent is to create a more focused delivery organization that can make operational decisions and move the project forward more efficiently. The same is being developed for the Arctic Economic Security Corridor, with Indigenous partners leading the way.


These are different approaches, but they recognize the same basic reality: major projects cannot simply be added to the existing workload and expected to move.


The people responsible for delivering regular government programs and services already have full-time jobs. Municipal and community administrators are managing water, roads, housing, emergencies, budgets, staff and council priorities. Territorial departments have their own programs, capital plans and operational responsibilities. Asking those same people to deliver once-in-a-generation projects from the side of their desks is not realistic.


Whether the answer is a dedicated internal team, a temporary secretariat, an arm’s-length delivery agency or outside project support (i.e.: Colliers Project Leaders) will depend on the project. What matters is that the owner has clear authority, focused leadership and enough capacity to keep making timely and informed decisions.


Northern Conditions Have to Be Part of the Plan


Northern logistics are sometimes discussed as though they are a cost adjustment added near the end of an estimate. They are much more than that. A shortened winter-road season can change an entire construction plan. Low water can disrupt marine resupply. Wildfires can interrupt transportation, displace workers and redirect local resources. Housing shortages can limit the number of workers a community can accommodate. A delayed piece of equipment that doesn't arrive next week; may very well miss the entire season.


These are not unusual events around the edges of a project. They are part of the environment in which the project must be designed and delivered. Access, logistics, labour, housing, utilities, climate conditions and local business capacity need to influence the project from the beginning. If they are considered only after funding is secured or a contractor is selected, they are no longer planning considerations. They have become project problems.


The same is true of cost. An early estimate based mainly on southern assumptions can create expectations that follow a project for years. By the time Northern conditions are properly included, the revised number is described as an overrun, even though the original number may never have reflected the real project.


Readiness means testing those assumptions before they become commitments. It means understanding not only what the project should cost to build, but what it will require to operate and maintain over time. If a government or community will eventually be responsible for that infrastructure, those obligations need to be understood before an agreement is signed.


Projects Do Not Move on Political Timelines


Political and economic attention moves in cycles. Governments change, commodity prices rise and fall, security concerns intensify, and funding programs open and close. A project considered nationally important today may still be important five years from now, but it may not receive the same level of attention.


That creates a difficult balance. Northern projects cannot be rushed through important planning, engagement or regulatory work simply to meet a political moment. At the same time, they cannot wait until every dollar is confirmed before beginning the early work required to become credible.


The real race is not necessarily between one Northern project and another. It is between the speed of the opportunity and the speed of preparation.


That is why planning money, feasibility work, governance discussions, site investigations, Indigenous and community engagement, and delivery and procurement planning all matter. They may not produce a groundbreaking ceremony, but they allow a project to move when the larger opportunity arrives.


Readiness Is Also About Control


Project readiness is usually presented as a way to obtain funding sooner. It is also a way for Northern project owners to maintain control.


An organization with a clear business case, established governance, strong partnerships, reliable cost information and an informed delivery strategy can engage governments, investors and contractors from a position of confidence. It understands what it is trying to accomplish, which decisions have already been made and which remain open. It also knows where outside expertise is needed without surrendering ownership of the project.


Most importantly, a prepared project owner can explain the Northern outcomes the project is expected to produce, whether those are better services, lower costs, stronger communities, Indigenous participation, local employment, economic development or improved security.


Without that preparation, outside timelines and funding conditions can begin defining the project. The owner may find itself responding to someone else’s process instead of advancing its own priorities. Readiness allows the North to move faster, but it also allows the North to set the terms of that movement.


What Being Ready Means


A project-ready organization does not have every answer, but it knows why the project is needed and what success should look like. It knows who owns the project, who makes decisions and who will operate it. It has begun the necessary Indigenous, community, government and regulatory conversations.


Its scope, cost and schedule have been tested against Northern conditions, and its procurement approach reflects the actual market. Its plans for local and Indigenous participation are more than a paragraph added to a tender document. It has identified the major risks, is honest about the work still to be done and has enough internal capacity, or the right outside support, to keep making informed decisions as the project moves forward.


That is the difference between a project that appears ready on paper and one that can withstand the realities of delivery.


The Opportunity in Front of Us


The North does not lack vision, worthwhile projects, capable people or communities that understand what they need. What has often been missing is sustained investment and the early capacity required to turn those needs into projects that are ready to move.


We now have an unusual combination of national security interests, economic priorities, critical-mineral demand, Indigenous economic leadership and overdue infrastructure investment. We should welcome that opportunity, but we should also understand what it requires from us.


The groundbreaking ceremony may be the first part of a project that most people see. The real beginning usually happens much earlier: establishing the right governance, completing a site investigation, holding an important conversation, preparing a realistic estimate, making a community decision or giving the project owner the capacity needed to lead.


The work before the work does not slow a project down. Done properly, it is what allows the project to move, and what keeps the North in control of where it goes.

 
 
 